Precast concrete erection happens fast — elements are set, shimmed, and often grouted in rapid sequence. The inspector who is not documenting in real time will be reconstructing from memory at end of day, and the bearing seat elevation that was 1/4 inch low on panel C-12 will not be remembered accurately enough to defend a decision. Field documentation must keep pace with the work.
What does a precast concrete installation inspector document?
A precast concrete installation inspector documents: bearing seat elevations before element placement; connection hardware type and installation conformance; plumb measurements on vertical elements; plan alignment relative to building grid lines; joint widths between panels; and any damaged or non-conforming precast elements. Welded connections require a separate weld inspection record by a CWI. All records are compiled into a closeout package submitted to the engineer of record before final acceptance.
Bearing seat elevation is the first verification checkpoint in precast installation. The bearing seat — the concrete ledge, steel corbel, or bearing pad surface that receives the precast element — must be at the correct elevation before the element is set. A bearing seat that is too low results in a panel top that is low; a seat that is too high may compromise bearing length.
Documentation steps for bearing seat elevation:
Precast connection hardware — mechanical anchors, welded plates, grouted inserts, and bolted connections — must be inspected and documented before the connection is covered, grouted, or concealed. The connection is the load path; once it is covered, the inspection opportunity is gone.
| Connection Type | What to Document | Hold Point? |
|---|---|---|
| Welded plate connections | Weld size, length, visual inspection result per AWS D1.1; CWI signature required | Yes — before paint or fireproofing |
| Bolted connections | Bolt size, grade, torque (if specified), washer presence, nut engagement | Yes — before grouting or covering |
| Grouted connections | Grout type, mix proportions, grout flow/consistency, date poured | Yes — document before grout placement and again after cure |
| Mechanical anchors into existing concrete | Anchor type, embedment depth, torque or proof load per ICBO/ICC-ES report | Yes — before covering |
Plumb and plan alignment are verified after each element is set and before adjacent elements constrain the position. The window for adjustment closes quickly in precast erection.
For each panel or column, record:
Plumb measurements taken with a 4-foot level are not accurate enough for compliance documentation — use a total station reflectorless measurement or a calibrated digital plumb bob for vertical elements over 15 feet.
The precast installation closeout package is submitted to the engineer of record for final acceptance. Required components:
Sitemark assembles precast installation inspection records from field entries, generates the closeout package, and routes it to the engineer of record for sign-off — without the manual collation that typically delays closeout on complex precast projects.
Sitemark captures bearing seat elevations, connection records, and plumb measurements as elements are set — so the inspection record is complete by end of day, not reconstructed from notes a week later.
Start Free Trial