The RFI is the formal record of every question, conflict, and design gap that surfaces during construction. A well-documented RFI log is the difference between a project that processes change orders efficiently and one that ends in a dispute because nobody can establish when a question was asked, when the answer came back, or whether work was performed at risk. Field engineers who understand RFI documentation protect their companies even on projects where the design was incomplete.
What must an RFI contain on a construction project?
A construction RFI must contain: a unique sequential RFI number; project name and contract number; date submitted; requesting party name; a clear description of the question or conflict with references to the specific drawing sheet, detail number, and specification section; the specific information requested; the contractor's proposed resolution where applicable; the response-required date to avoid schedule impact; and the name of the person or firm the RFI is directed to. RFIs that lack drawing references or ask compound questions are commonly returned without response.
An RFI that omits critical information will be returned, rejected, or ignored — adding days to the response cycle and compressing the construction schedule. Required content fields:
| Field | Content Requirement |
|---|---|
| RFI number | Sequential number; never reuse or skip numbers. The log must account for every number in sequence. |
| Date submitted | The date the RFI is transmitted to the architect, engineer, or GC. Not the date it was drafted. |
| Title | Brief, specific description: "Foundation drain direction at Grid B-7" is better than "Drain question." |
| Description of question or conflict | State what the contract documents show (with specific drawing and spec references) and what the conflict or ambiguity is. Include markup sketches where applicable. |
| Drawing and specification references | Sheet number, detail number, and specification section that the question relates to. Without these, the respondent cannot locate the referenced condition. |
| Proposed answer | The contractor's suggested resolution. This is not mandatory, but RFIs with a proposed answer are typically responded to faster and more favorably. |
| Required response date | The date by which a response is needed to avoid work stoppage or schedule delay. This establishes the baseline for delay claims if the response is late. |
| Directed to | The specific person or firm responsible for answering — architect, structural engineer, MEP engineer, or GC depending on the question. |
The RFI log is the master tracking document for all RFIs on a project. It must be maintained in real time — not assembled retroactively at closeout. A well-managed RFI log includes:
Poorly written RFIs waste time on both sides of the question. The most common RFI writing failures and how to avoid them:
| Common Failure | Better Practice |
|---|---|
| Compound questions: "Please clarify the slab thickness, rebar layout, and top-of-slab elevation" | One question per RFI. Each separate issue gets its own RFI number and tracking. |
| No drawing reference: "The grading plan is unclear" | Reference specific sheet: "Civil Drawing C-3, Detail 2/C-3 shows finish grade elevation as 104.5, but the drainage flow arrow points uphill. Confirm design intent." |
| Answer embedded in question: "Please confirm the invert is 98.3 as installed" | An RFI is a question, not a CYA. State the conflict and ask for the answer — do not assume. |
| No required response date | Always include the date by which a response is needed. If the work is imminent, note the pour date or schedule milestone. |
| No proposed resolution | Include a proposed resolution where the contractor has a preference. This moves the respondent toward a decision rather than requiring them to generate a solution from scratch. |
The RFI log is the starting point for change order substantiation. When an RFI response requires changed work, the process from RFI to change order must be documented in a traceable chain:
Sitemark's field documentation tools let field engineers log RFIs in the field with drawing attachments, track response status and dates, and link RFI records to daily field reports that document schedule impacts — creating the contemporaneous documentation chain that supports change order approvals.
Sitemark captures RFI submissions, response dates, and linked field report entries — giving your project team the contemporaneous documentation chain that makes change orders approvable and disputes avoidable.
Start Free Trial