Curb and gutter grade documentation is a control point between subgrade and paving on road construction projects. A curb flowline that is out of grade creates drainage problems — ponding at high spots, excessive flow at sag points — and may require removal and replacement before the road can be paved. Documentation before and after the pour is what proves the work was done to grade.
What documentation is required for curb and gutter grade on a DOT road project?
DOT curb and gutter grade documentation requires three records: (1) a pre-pour subbase elevation survey at the curb line on a 25-ft grid, confirming the subbase is within ±0.05 ft of the design curb subgrade elevation before forms are set; (2) a post-pour flowline elevation survey at 25-ft intervals and at all PC/PT points, sag points, and grade breaks, with deviations compared to the design profile and shown in a deviation table; and (3) a back-of-curb or top-of-curb elevation check at the same stations as the flowline survey, confirming curb height is within tolerance. State DOTs typically require the flowline deviation report to be submitted to the resident engineer before paving begins. Acceptable tolerance is typically ±0.04 ft for the flowline and ±0.25 inch for curb height.
The subbase elevation at the curb line determines whether the poured curb will achieve the design height and flowline. If the subbase is high at any point, the curb will be under-height at that point — and the flowline will be correspondingly high, causing water to pond at that location instead of flowing to the inlet.
Pre-pour survey procedure:
The post-pour flowline survey is the QC record that the inspector signs off on before paving can begin. The flowline is the inside bottom of the gutter pan — it must drain continuously toward each inlet without high spots or flat spots that would allow standing water.
| Location Type | Survey Interval | Why Closer Spacing |
|---|---|---|
| Tangent sections | 25 ft | Standard interval for straight grades |
| Horizontal curves | 10 ft | Cross slope and flowline vary through curve |
| Sag vertical curves | 10 ft | Critical to catch flat spots at low point |
| Curb returns (driveway aprons) | At each edge and center | Match point must drain to road, not pond |
| Inlet locations | 5 ft each side of inlet | Confirm grade breaks drain to inlet |
| PC and PT of horizontal curves | At PC and PT | Transition from tangent to curve grade |
When flowline shots exceed the tolerance, the options are limited and none of them are cheap:
The documentation package submitted to the resident engineer or inspector for curb and gutter sign-off typically includes:
Keep the signed curb and gutter QC record as part of the project documentation package. This record is your evidence that the curb was accepted before paving — if paving elevation issues arise later, the curb acceptance record proves the problem originated after your work was signed off.
Sitemark captures flowline shots, deviation tables, and corrective action records in the field — assembled into a sign-off package before the paving crew arrives. Start free.
Start Free Trial