200 acres
Site area
2,400
Piles per project
±25 mm
IFC tolerance
4 hrs vs 3 days
Verification time
A regional EPC contractor specializing in utility-scale solar was awarded a 200-acre project in the Southwest. The design called for 2,400 driven piles, each with a precise finished-grade elevation defined in the issued-for-construction (IFC) drawings. Structural tolerances were tight: any pile elevation more than 25 mm outside design called for a corrective action before module installation could begin.
Getting that verification right mattered beyond quality. If a pile deviation was missed in the field and caught during the engineer's as-built review, the corrective work — re-driving or cutting — happened after the module crew had already mobilized. That sequencing risk translated directly into project delay and liquidated damages exposure.
The previous workflow was built on a shared Excel file. Two field technicians would collect pile elevations throughout the day using a Topcon total station, record them on a paper tally sheet, then enter them into the spreadsheet at the end of the shift. A project engineer would compare each row to the design elevation, flag deviations by conditional formatting, and compile a summary for the client's construction manager.
On a 2,400-pile site, that process consumed three full working days — typically spread across the week when pile driving was completing. The lag meant that a deviation discovered on a Wednesday might not be reviewed and actioned until Friday afternoon, putting the module installation schedule at risk.
Accuracy was also a concern. Manual data entry across two shifts and multiple personnel introduced transcription errors. The team caught several during QA review, but the process to trace a suspect entry back to field notes added hours of rework.
The contractor piloted Sitemark mid-project on a block of 400 piles. Field technicians logged elevation shots directly from the total station into Sitemark using the pile elevation checker. Each shot was tied to a pile ID, compared to the imported design elevation in real time, and flagged immediately if it exceeded the ±25 mm tolerance.
Deviations appeared on-screen the moment they were logged. The field crew could respond immediately — document, flag for re-drive, or confirm as accepted with a note — rather than waiting for the end-of-day compilation. Pile IDs with open deviations showed in a live dashboard that the project engineer monitored from the site office.
When the block was complete, the as-built report generated in a single export: every pile ID, design elevation, measured elevation, deviation value, and pass/fail status, formatted as a PDF ready for the engineer's stamp.
Verification of the 400-pile pilot block took under two hours, compared to roughly six hours under the spreadsheet workflow. On the full 2,400-pile count, the team completed verification in four hours across a single shift. The three-day window compressed to less than a half day.
Transcription errors were eliminated. Every data point originated in Sitemark from the total station operator, with no paper tally or manual re-entry step.
The client received a complete as-built PDF — not a shared spreadsheet — with deviation flagging and corrective action notes embedded. The engineer of record accepted it without a revision request.
The shift was not about replacing the field crew's workflow — it was about removing the layer between field data and the final document. When pile elevation, design comparison, and report generation happen in one step, the three-day lag disappears. The crew does the same physical work. The documentation catches up in real time instead of trailing behind by days.
Quick answer
How long does it take to verify pile elevations on a 2,400-pile solar site?
With a spreadsheet workflow, verification of 2,400 piles typically takes 3 full days of field data entry and engineering review. Using Sitemark's pile elevation checker with real-time deviation flagging and automatic as-built export, a regional EPC contractor completed the same verification in 4 hours — a reduction of more than 80%.
Running pile elevation verification on your next solar project?
Start 14-day free trialNo credit card required.